Genting signage featured in a report on a Malaysian court ordering slope repairs and halting construction on the Genting Sky City project. Photo: Wikimedia Commons / Public Domain.

A proposed high-rise development near one of Malaysia's busiest mountain resorts has encountered a significant legal obstacle after the High Court ordered restrictions on construction activities and remedial work to address damage to the surrounding hillside.

 

The dispute centers on the Genting Sky City project, a planned development involving hotels, commercial suites and parking facilities on land close to First World Hotel in Genting Highlands, Pahang.

 

The judgment favors three companies associated with the Genting group: Genting Highlands Bhd, Genting Malaysia Bhd and First World Hotels & Resorts Sdn Bhd. The defendants include contractor Sycal Bhd, developer GM Aero Support Sdn Bhd and four other parties involved in the development.

 

The court found that earthworks and alterations to the site's slopes had been carried out without the necessary valid permissions. It subsequently imposed restrictions on further excavation and slope modifications while requiring the affected areas to undergo restoration.

 

The ruling also carries financial consequences for the defendants, who were ordered to pay RM243,800 in general damages and RM2 million in legal costs.

 

However, the dispute is not necessarily the final chapter for the development. The defendants have challenged parts of the judgment, and the matter is awaiting further consideration by the Court of Appeal.

Subscribe to the Asia Casino News newsletter for the latest casino industry news, regulatory updates, and gaming market insights across Asia.

 

Genting Sky City project faces restrictions over hillside works

The proposed development is situated northeast of First World Hotel, with the site estimated to be approximately 100 meters from the existing property.

 

Plans submitted by the developers involved 10 building blocks, with hotels and commercial suites ranging from 27 to 56 stories. Parking facilities were also included in the proposed development.

 

Its proximity to existing resort infrastructure became a central issue in the legal proceedings.

 

The Genting companies argued that excavation, slope cutting and other construction activities could undermine the surrounding land and threaten nearby buildings and roads. Their concerns extended beyond the immediate construction site because the hillside supports established resort facilities.

 

First World Hotel, Sky Avenue, Arena of Stars and the Genting International Convention Centre are among the properties and facilities forming part of the wider resort environment.

 

The plaintiffs maintained that construction-related changes to the hillside could expose these assets to structural and environmental risks.

 

The court's decision focused on the actual condition of the affected slopes and the potential consequences of allowing further work to proceed without adequate safeguards.

 

Importantly, the injunction is a preventive legal measure. It allows a court to intervene when the evidence establishes a credible threat of future harm, rather than requiring the plaintiffs to wait for a major incident to occur.

 

Court identifies planning and construction compliance problems

A central element of the judgment concerned the legal permissions required for the development.

 

The court declared that the relevant earthworks and slope modifications were unlawful in the absence of valid approvals. It also found that the proposed development contravened applicable planning and building requirements.

 

The legal framework considered included Malaysia's Town and Country Planning Act 1976, the Street, Drainage and Building Act 1974, and national guidelines governing development in hillside and highland areas.

 

These requirements are particularly important in mountainous locations, where construction can involve substantial excavation, changes to natural drainage and the removal of existing ground support.

 

The court's findings made clear that obtaining permission for a development involves more than securing approval for the intended buildings. The associated earthworks and engineering arrangements must also comply with applicable regulations.

 

The defendants disputed the allegations during the proceedings. They argued that the legal action was an attempt to prevent competing development in Genting Highlands rather than a genuine effort to address safety concerns.

 

The court nevertheless granted the Genting companies substantial relief, including declarations concerning the legality of the works and restrictions on further construction activity.

 

Six-month deadline for slope restoration

One of the most significant parts of the judgment is the requirement to repair the affected hillside.

 

The defendants were directed to restore the relevant slopes within six months of the judgment through backfilling work using blockstones measuring at least nine inches.

 

The court also prohibited further excavation, slope modifications and the use of specified support structures in connection with the disputed works.

 

The restoration order addresses concerns about the physical stability of the land, rather than simply imposing a financial penalty for the disputed construction activity.

 

Evidence presented during the proceedings included water seepage, drainage conditions and the possibility that existing ground support could be compromised. These factors were relevant because occupied buildings, roads and other resort facilities are located near the development area.

 

A court-appointed expert assessed the condition of the slopes and concluded that strengthening was necessary before construction could proceed in any phase of the proposed development.

 

The judge considered these findings important when determining whether preventive intervention was justified.

 

The decision also rejected the argument that the absence of a landslide or structural collapse during the proceedings demonstrated that the site was safe. Construction had been restricted during the relevant period, making the absence of such an incident insufficient to establish that the underlying risks had disappeared.

 

Financial consequences follow lengthy legal proceedings

The case has involved a prolonged legal process since the Genting companies initiated proceedings in February 2020.

 

The trial lasted 76 days and included testimony from engineering and other professional witnesses. Six witnesses testified for the plaintiffs, while nine appeared for the defendants.

 

The court ordered the defendants to pay RM243,800 in general damages relating to the slope damage and RM2 million in legal costs.

 

The ruling did not grant every remedy requested by the Genting companies. Their claims for exemplary damages were dismissed, as was the defendants' counterclaim.

 

That counterclaim challenged the legal action as an abuse of court proceedings and alleged that the plaintiffs were attempting to prevent development and eliminate competition in the resort area.

 

The outcome therefore represents a substantial victory for the Genting companies, but it also reflects a decision limited by the evidence and legal remedies considered during the trial.

 

Earlier planning-related challenges had also failed to stop the development through the Pahang Planning Appeal Board. Appeals filed by Genting and Genting Malaysia were struck out in April 2021.

 

The subsequent High Court judgment addressed the separate issues surrounding the earthworks, slope conditions and compliance with development requirements.

 

Appeal keeps the development's future unresolved

The defendants are appealing parts of the High Court decision, leaving the legal dispute open.

 

The written grounds of judgment, running to 275 pages, were dated October 29 and uploaded to the judicial system on November 16.

 

The appeal means that further proceedings could affect how parts of the ruling are ultimately applied. However, the existing orders remain important while the challenge proceeds. A separate application to suspend the judgment pending appeal was dismissed on October 12.

 

For the developers, the immediate challenge involves complying with the restoration requirements and construction restrictions imposed by the court.

 

For Genting Malaysia, the case concerns the protection of an established resort destination and its surrounding infrastructure. The company operates within a location where hillside conditions, drainage and access routes are important to the continued operation of its hospitality and entertainment facilities.

 

The dispute also highlights the additional responsibilities associated with building large projects in mountainous tourism areas. Developers must consider the effects of excavation and structural work on neighboring properties, not just the feasibility of the proposed buildings.

 

The Genting Sky City project now faces a combination of legal, engineering and development challenges. Its longer-term prospects will depend on the outcome of the appeal, compliance with the restoration orders and the ability to satisfy the applicable planning and construction requirements.

 

For Malaysia's integrated resort sector, the case offers a reminder that major development plans can face serious setbacks when construction compliance and hillside safety become central issues in court.


About Asia Casino News


Asia Casino News covers developments across the casino, iGaming, betting, regulation and gaming industries in Asia and international markets. Our coverage follows the legal, regulatory and commercial changes shaping the global gambling industry. Visit Asia Casino News for more industry news, analysis and gambling guides.


Contact Asia Casino News for editorial inquiries, partnerships, news tips, or feedback about our coverage of the Asian gaming industry.

Sources
  • The Edge Malaysia

Comments


ACN_1500x160.jpg
aupwe_color_game_600x100.png
Truepay-Magazine-Ads.gif
GIH -606x94 px.gif
iGBAwards_Banners_600 x 100.png
bottom of page